STEP:UP
Funding mechanism | Network Innovation Allowance (NIA) |
---|---|
Duration | Jul 2025 - May 2026 |
Estimated expenditure | £257,100 |
Research area | Optimised assets and practices |
STEP:UP is assessing the viability of operating electricity distribution networks at 220 kV. 220 kV would establish greater electricity distribution capacity and optimise assets and practices which could move the energy transition forward. It could also reduce the generation connection queue faster than restricting distribution voltage to 132 kV.
Problem(s)
This project will examine whether the use of 220 kV distribution circuits could enable faster generation connections and cost-effective reinforcements compared to conventional operation and reinforcement at 132 kV. Some existing 132 kV routes were installed using towers that are capable of use at 275 kV. These circuits may be better utilised if operated at 220 kV.
This project is the discovery phase, with the primary aim of establishing whether it is worthwhile to proceed with further investigations and trials. Electricity distribution at 220 kV would require updates to the Electricity Act. The method below describes how the project is structured to test assumptions and provide guidance for decision making.
Method(s)
This discovery phase project will perform an initial investigation into the viability of 220kV alongside a case study of its use in a location which has existing towers potentially capable of operating at a higher voltage than the existing 132 kV. The project will be delivered in the following workstreams:
- Physical considerations - Examination of the physical requirements and possible solutions to enable operation at 220 kV.
- Regulation and Legislation - Examination of barriers and changes required to licenses and legislation
- Design, planning and process impact - Review of DNO processes and standards that would be impacted via the introduction of a new system voltage
- Supply Chain considerations - Assessment of the supply chains’ capability to provide 220 kV equipment to UK DNOs
- Business Case - Initial derivation of the 220 kV solutions’ cost benefit analysis (CBA).
Proposed project deliverables are as follows:
Deliverable 1 ASSESSMENT OF CIRCUIT CONSIDERATIONS AND APPLICATION NUMBERS
To gain understanding of the routes within the NGED license areas that the 220 kV solution could be applied to. The deliverable will be in three parts:
A. Route knowledge:
To review the number, composition and features of the existing and potentially relevant routes in the NGED license area, so that the solution applicability can be determined and an understanding of the requirements for uprating to 220 kV obtained.
The first section of the report will detail the salient features of the applicable routes, such as:
Overhead Circuits
- The tower types used and the numbers of each,
- Circuit composition in terms of the numbers of terminal, suspension and angle towers of each tower type.
- Consideration of mid-circuit cable sections.
- The circuits carried on the route and considerations of the associated circuit ends.
- Infrastructure/river crossings and any spans where clearances may require special treatment.
- 132 kV customer considerations.
- Consideration of the application of condition assessment data
- Consideration of potential access or land ownership issues.
- Consideration of the existing or anticipated thermal or voltage constraints on the routes between now and 2050 and how operating at 220kV may affect the distribution network.
Underground Circuits
- Cable types available and considerations for underground circuit refurbishment from 132kV to 220 kV.
- Requirements for new 220 kV underground cable routes.
- Consideration of mid-circuit overhead sections.
- Consideration of the associated circuit joints & cable terminations.
- Infrastructure/river crossings and any spans where 220kV cabling may require special treatment.
- 132 kV customer considerations.
- Consideration of the application of condition assessment data
- Consideration of potential access or land ownership issues.
- Consideration of the existing or anticipated thermal or voltage constraints on the routes between now and 2050 and how operating at 220 kV may affect the distribution network.
B. Technical requirements for 220kV uprating
The second part of the report will present proof of concept designs for options to accommodate 220kV on the identified routes.
- An indicative design option for converting each of the 275kV capable tower type families to 220kV operation, with an estimate of costs for conversion and the capacity delivered.
- Identification of any engineering challenges associated with terminal/suspension/angle towers or any route features as identified in Part A.
- If identified as applicable, presentation of design options for converting 132 kV capable tower type families and associated cabling requirements to 220 kV operation, with an estimate of costs for conversion and the capacity delivered. This would include a literature review to identify available solutions, including innovative solutions such as insulated cross-arms, as well as conventional solutions such as the modification/rebuild of towers.
- Identification of any engineering challenges associated with terminal/suspension/angle towers and cables as identified in Part A.
- If identified as applicable, presentation of options for uprating of mid-circuit cables, including modifications to the cable sealing end compounds, with an estimate of costs for conversion and the capacity delivered.
- Initial estimates of the costs to implement the design solutions.
C. XW Route 220 kV uprating research study
Evaluation of global standards implemented for 220 kV in other regions with a selection of the preferred standards
- complying to the UK weather and European codes. Following this, the project will:
- Summarize the list of modifications required on 132 kV XW OHL for uprating to 220 kV.
- Summarize the modifications required on Insulator sets, earth wire, tower cross arms and earth wire shielding angles.
- Undertake CAD modelling considering the above changes.
- Check for the clearance infringements with reference to new 220 kV guidelines.
- Highlight the clearance infringements and other constraints for existing line using existing conductor.
- Check for the clearance infringements with reference to new proposed conductors and summarize the issues in an OHL report.
- High level assessment on tower modifications and provide recommendations for next stage of detail design.
- High level assessment on foundations and provide recommendations for next stage of detail design.
Deliverables:
- OHL Report, with clearance infringement and recommend.
- Profile Drawings only for spans with clearance issues.
DELIVERABLE 2 ASSESSMENT OF SUBSTATION CONSIDERATIONS AND APPLICATION SPECIFICS
To gain understanding of the requirements to, and viability of, 220 kV interface implementation in substations. This would include two parts:
A. Network interface requirements:
To identify the topology and equipment types required at substations to interface to 220kV circuits.
The first part of the report will present proof of concept connection designs via single line diagrams and representative layouts for connection to 220 kV single and double OHL and underground cable circuits. This will include details of the proposed:
- Switchgear types, ratings and configurations,
- Transformer physical size and ratings.
- Cross-site cabling/GIB option requirements.
- Interface equipment to the existing infrastructure
- Initial estimates of the costs to implement the design solutions.
B. Viability assessment of the sites identified in deliverable 1 to accommodate 220kV interface.
The second part of the report will review the substation sites identified in Deliverable 1 to understand which and how many of the sites are suitable to be extended, either within the existing land ownership boundary or onto surrounding land.
DELIVERABLE 3 ROADMAP OF REQUIREMENTS FOR REGULATORY AND LEGISLATIVE CHANGE
Identification of the non-technical documents requiring adjustment to accommodate 220kV use for distribution, and outline of the process, timescales and costs for modification. This will include relevant legislation, network licenses, regulatory documents, safety, training and other workforce considerations e.g.:
- The Electricity Supply Regulations (1988)
- The Electricity Act (1989)
- Ofgem license conditions
DELIVERABLE 4 ROADMAP OF REQUIREMENTS FOR TECHNICAL DOCUMENTATION CHANGES
Identification of the technical documents requiring adjustment to accommodate 220kV use for distribution, and outline of the process, timescales and costs for modification. This would include network design and planning documents, operational procedures, equipment specifications etc.
Example documents include:
- ENA Engineering Recommendation P2, particularly where 220kV operation may cross a class of supply boundary and necessitate increased network redundancy requirements.
- The Electricity Safety, Quality and Continuity Regulations (2002)
- The Distribution and Grid codes
- NGED Operational procedures
- NGED Network planning standards
- NGED Equipment specifications
- ENA Engineering Recommendations P18, P28, P29 etc.
DELIVERABLE 5 INVESTIGATION INTO THE 220KV SUPPLY CHAIN
Identification of 220kV equipment manufacturers (e.g., transformers, switchgear, OHL conductors and insulators, cables, joints etc) and assessment of any barriers preventing supply to the UK.
This will include consideration of the cost and timescales for adapting the supply chain to delivery 220kV projects (e.g. training requirements) against the improvement in capacity delivery.
DELIVERABLE 6 DETERMINATION OF THE SOLUTION COSTS AND BENEFITS VIA THREE CASE STUDIES.
Examination of three representative 220kV projects, to determine implementation requirements (including costs and timescales) such that a comparison against other solutions providing the same capacity can be made.
The 3 case studies will be selected to explore the sensitivities of the solution, to understand the factors affecting its effectiveness. Each of the case studies will include, for both the 220kV solution and a counterfactual conventional solution providing the same capacity increase:
- a description of the project solutions and the work required to implement each, highlighting the physical and logistical pros and cons of each (e.g., land requirements).
- Cost of solution - For the 220kV solution this would include a proportion of the costs identified in workstreams 2, 3 and 4.
- Timescales for delivery of each solution, highlighting any benefits associated with faster delivery,
- Network studies to confirm that both solutions provide the similar capacity benefits and identification of any adjacent constraints that are introduced or removed.
Deliverable will include assessment of the number of applications in the UK to determine whether the level of effort identified in workstreams 2, 3 and 4 is justifiable.
FINAL REPORT
A final report will consolidate the project deliverables into a document which may inform and support investment decisions by providing recommendations for next steps.